Chapter:
estimating-and-costing-loksewa-mcqs
1. The measurement of steel grills is taken in terms of
2. The quantity of damp proof course (D.P.C.) is worked out in
3. When not specified, volume of steel in R.C.C. work is taken as
4. The technique of finding fair price of an existing building or property is known as
5. When contractor fails to complete work, an agency is employed to execute a part or whole of work at cost of contractor. Such an agency is known as
6. When contractor fails to complete work, an agency is employed to execute a part or whole of work at cost of contractor. Such an agency is known as
7. When contractor fails to complete work, an agency is employed to execute a part or whole of work at cost of contractor. Such an agency is known as
8. The concealed faces of frames of doors and windows are painted with
9. The …… value of a property is amount of money whose annual interest at highest prevailing rate of interest will be equal to net income from property.
10. The amount required to be deposited by a contractor while submitting a tender is known as